Roadmap

Milestone: imagej2-b8-analysis

4 years late (10/25/13 18:00:00)

88%

Number of tickets:
closed:
256
active:
36
Total:
292

Beta release focusing on image analysis and processing routines: thresholding, measurements, etc.

Milestone: imagej2-b9-rois

4 years late (12/20/13 18:00:00)

56%

Number of tickets:
closed:
37
active:
29
Total:
66

Beta release focusing on regions of interest.

Milestone: imagej2-b10-compatibility

3 years late (02/28/14 18:00:00)

49%

Number of tickets:
closed:
41
active:
42
Total:
83

Beta release focusing on completeness of functionality, especially migration of ImageJ1 features in a backwards compatible way when feasible.

Milestone: imagej2-b11-docs

3 years late (04/25/14 18:00:00)

75%

Number of tickets:
closed:
12
active:
4
Total:
16

Beta release focusing on completeness of documentation and tutorials.

Milestone: imagej2-unscheduled

3 years late (06/13/14 18:00:00)

51%

Number of tickets:
closed:
61
active:
59
Total:
120

This is not a true milestone. It is a place to temporarily put tickets during major reorganizations of the ticket database. These reorganizations typically happen after beta releases. Tickets should be assigned from here into other milestones as quickly as possible.

Milestone: imagej-2.0.0

3 years late (06/13/14 18:00:00)

74%

Number of tickets:
closed:
93
active:
32
Total:
125

First stable release of ImageJ2.

Milestone: imagej-2.1.0

3 years late (01/01/15 00:00:00)

50%

Number of tickets:
closed:
3
active:
3
Total:
6

Post-2.0.0 release of ImageJ2, for high-priority features and improvements.

Milestone: imagej-2.5.0

19 months late (01/01/16 00:00:00)

80%

Number of tickets:
closed:
37
active:
9
Total:
46

Intermediate release after 2.0.0, with new features and bugfixes.

Milestone: imagej-3.0.0

7 months late (01/01/17 00:00:00)

60%

Number of tickets:
closed:
6
active:
4
Total:
10

Later release for longer term goals and ideas.

Note: See TracRoadmap for help on using the roadmap.